Am I correct in understanding that in order to determine Payload PM, SE, MA [e.g., WBS 5.1, 5.2, 5.3], Payload I&T/GSE [e.g., WBS 5.5, 5.6], Spacecraft PM, SE, MA [e.g., WBS 6.1, 6.2, 6.3], and Spacecraft I&T/GSE [e.g., WBS 6.6] costs, each user must export TP results into an Excel spreadsheet, then apply their own factor to obtain the aforementioned WBS costs because TP lumps all of those costs into 1 PM bucket, 1 SE bucket, 1 MA bucket and 1 I&T bucket? And we have to do this every time we make a change to determine those costs?

Gosh No and No!  You can view these Resource x Activity costs _by_ System as in the following—

06. SPACECRAFT SYSTEM


05. PAYLOAD SYSTEM

Of course, for reporting purposes, if you _do_ want to combine them into one set of buckets, then do the same Resource x Activity view at the (combined) top-level Folder—


TOTAL = SPACECRAFT SYSTEM + PAYLOAD SYSTEM